NVIDIA H200 (Hopper Refresh)
Product Overview
The NVIDIA H200, released in 2024, is a memory-upgraded version of the H100. The key change is the upgrade from 80GB HBM3 to 141GB HBM3e, with bandwidth increasing from 3.35 TB/s to 4.8 TB/s (+43%). This delivers significant performance gains for 70B+ parameter model inference, enabling single-GPU loading of longer contexts.
Core Specifications
| Parameter | Value |
|---|---|
| Architecture | Hopper GH100 (refresh) |
| Process Node | TSMC 4N |
| Transistor Count | 80 billion |
| Memory | 141 GB HBM3e |
| Memory Bandwidth | 4.8 TB/s (4,800 GB/s) |
| CUDA Cores | 16,896 |
| Tensor Cores | 528 (4th Gen) |
| FP8 Tensor Core | 3,958 TFLOPS (sparse) |
| TDP | 700 W (SXM5) |
| Interconnect | NVLink 4.0 (900 GB/s), PCIe 5.0 |
| MIG | Up to 7 instances |
| Form Factor | SXM5 / PCIe 5.0 |
H100 vs H200 Comparison
| Metric | H100 | H200 | Improvement |
|---|---|---|---|
| Memory Capacity | 80 GB | 141 GB | +76% |
| Memory Type | HBM3 | HBM3e | Faster |
| Memory Bandwidth | 3.35 TB/s | 4.8 TB/s | +43% |
| FP8 Compute | 3,958 TFLOPS | 3,958 TFLOPS | Same |
| Price (Reference) | ~$25,000–30,000 | ~$30,000–35,000 | +20% |
Vendor Information
| Parameter | Value |
|---|---|
| Manufacturer | NVIDIA Corporation |
| Official Website | https://www.nvidia.com |
| Product Page | https://www.nvidia.com/en-us/data-center/h200/ |
| Release | November 2024 (first shipments) |
Software & Drivers
- Fully compatible with the same CUDA toolchain as H100
- Driver download: https://www.nvidia.com/Download/index.aspx
- Recommended CUDA 12.4+ for optimal HBM3e performance
Use Cases
- Large model inference (70B+ single GPU)
- Long-context (100K+ tokens) inference
- Large model fine-tuning
- HPC memory-bound workloads
November 2026 Update: Import Approvals and Secondary-Market Pricing
Reuters reported on November 5 that roughly 600,000 H200 accelerators are sitting in warehouses in Hong Kong, China, because mainland authorities have not approved large-scale imports. U.S. rules permit exports to approved Chinese customers, but only narrow licences have been issued — Alibaba, ByteDance and Tencent each received about 10,000 units for training use only. The same reporting puts eight-GPU H200 servers above 6 million yuan on the secondary market, roughly three times the price a year earlier. Follow-up reporting on November 7 says about 24 Chinese companies have been cleared to buy or handle H200 chips, with some registered offices apparently vacant and ownership links to restricted entities, raising questions about licence due diligence.
All of the above is press reporting, not a first-party regulatory or NVIDIA document; the stockpile size, prices and company list are unconfirmed and are not entered into the specification table. For buyers, compliant-channel lead times and transaction prices are volatile — re-quote quarterly and compare against the H20 and domestic alternatives in the full comparison table.
Related Comparisons
- NVIDIA H100 — Previous generation
- NVIDIA B100 / B200 — Blackwell successors
- AMD MI325X — Direct competitor
2026-11-19 update: $2.4B from China in the quarter, zero in guidance
The FY2027 Q3 results published on November 17 disclose $2.4B in revenue from licensed Hopper data center products sold into China. Q4 guidance is $130B plus or minus 3% and explicitly assumes no data center compute revenue from China. Read together, the message is clear. This is not a demand call; the company is leaving no room for that revenue in guidance.
The call also added a pricing datapoint. Hopper GPUs have recontracted under multi-year agreements at up to twice their original price, while token prices have dropped nearly 60% since May and rental rates across GPU generations have been rising. For customers still running H-series clusters, renewal cost and new purchase cost are no longer on the same curve.
Sourcing note: the $2.4B figure is company-disclosed revenue for licensed Hopper products in China, with no model split. "Twice the original price" is the upper end of a recontracting range described on the call, not a list price. Nothing here changes the spec table.
2026-11-25 update: tripled gray-market prices and write-down exposure
Against the backdrop of roughly 600K units stranded in Hong Kong, three new data points emerged in mid-November:
- Gray-market quotes: 8-GPU H200 servers quoted above 6 million yuan (~$900K) in China, roughly triple a year ago (channel-source citation; no completed-sale record).
- Small-batch deliveries: ByteDance and Tencent each received deliveries on the order of 10,000 units; even RTX PRO 5500 orders remain unfulfilled.
- Write-down exposure: NVIDIA booked a $400M charge in 1H FY2027 tied to excess inventory and purchase commitments; at an estimated $8,000-$11,000 per-GPU cost, 600K units carry a book value of $4.8B-$6.6B — the ceiling for potential further impairment (estimated, not company-disclosed).
Supply-chain chatter in the same window has NVIDIA slowing some chip orders, citing tighter export reviews and the Hong Kong stockpile, coinciding with the Rubin ramp-delay rumors; the company has not confirmed either.